I. Roofing Liner: The Building's "Second Line of Armor"
Think of the roofing liner as an important intermediate layer covering the structural purlins and placed below the top water tight layer. It should not only furnish a firm, smooth base for the waterproofing material but one which is strong enough to resist the wind and rain and the temporary loading due to workmen.
Common Problem
-
Sheet Material Selection Is Key:
Thickness and Strength:
On the whole, we would advise thicker sheets of at least 6mm for roofing liners. Thicker sheets (for example, 8 mm or more) may be necessary in regions of high wind pressure or snow load. Load always to be calculated in accordance with local building regulations and sheets to be chosen taking into account adequate bending strength.
Weather Resistance Is Paramount:
Always use weather-resistant fiber cement boards. They maintain excellent dimensional stability and strength in humid environments and will not powder or warp due to repeated wet–dry cycles. Non-weather-resistant boards should never be used outdoors or in locations prone to moisture.
Surface Treatment:
Use alternatively sandblasted sheets in order to get a rough surface. This helps to improve adhesion of waterproofing membranes (bitumen membranes and PVC/TPO films) to the substrate, prevents the glide on surfaces so as increasing the bond between them.
-

Construction: Details Matter
-
Frame Installation:
The batten supporting purlins (wooden or light steel joists) should be spaced to the span table recommended by the board manufacturer. Over sizing can cause the boards to be weak, vibrate or possibly break. As a rule of thumb the center to center spacing of roof joists shall not exceed 610mm when 6 mm boards are used for roofing.
Laying and Fixing:
The long sides of the boards must be supported by the joists, and the short-end joints should fall at the center of the joists.
Leaving gaps is crucial! an expansion gap of 3–5 mm should be ensured between the boards at all four edges. Fiber cement boards will expand and compress between seasons, it is recommended to leave a 3/8″ gap at edges; undrained by weep holes.
Fix hence fixing with corrosion-resistant special screws (as stainless or galvanized self-tapping screws). Screws should be a minimum of 10 mm (0.39 in) from the edge of board and 15 mm (0.59 in) from the corners. They need to move through the joists with a good sense of depth, but should not be cranked too tight in fear they might collapse the board.
Joint Treatment:
For roofs with high waterproofing requirements, it is recommended to use high-quality construction sealant to fill the gaps between boards, forming a more continuous base layer. In addition, all board edges and cut openings should be properly sealed to provide moisture protection.
II. Floor Substrate: The Quiet and Solid "Stage Foundation"
The floor substrate is the hidden foundation that supports the final finishing layer (wood flooring, tiles, carpet, etc.). It is critical to floor flatness, sound insulation, and the overall solidity underfoot.
Core Requirements of the Board:
Thickness and load-bearing capability:
Cement fiber boards for floors are mostly 12 mm for residential purposes; however, the commercial area may call for 15 mm, 18 mm, or even thicker boards. The main features are top-notch impact and bending tension that allow the fiber cement panel to spread the concentrated load and thus prevent the local depression.
Water resistance, good dimensional stability:
Generally, even the inner parts of floors can get wet or have liquid spilled on them. So, it goes without saying that we must choose the boards which have high-density and low-absorption. That is a very effective way to resist moisture penetration, prevent board's warpage, and at the same time keep the wood finish (in case of solid wood floor) protected.
Surface Quality and Health:
The floor baseboard should have a dense, flat surface to facilitate finishing application and installation. At the same time, it must meet the strictest indoor air quality and environmental standards of the country of origin (e.g., low VOC emissions and asbestos-free certification).

Installation for a Seamless Finish:
Base Preparation:
Whether using a timber frame or a cement mortar leveling layer, the base must be firm, dry, and flat. Any unevenness will be transmitted to the finished surface.
Laying Direction:
Boards should be laid perpendicular to the underlying support joists to maximize structural strength. Joints should be staggered to avoid continuous cross-joints.
Fixing and Spacing:
Use corrosion-resistant screws similar to those used for roofing, fastening the boards to each joist at intervals of 150–200 mm. Likewise, a 2–3 mm expansion joint must be left around the perimeter and between boards. This gap can be filled with grout to achieve a continuous, stable, and noise-reducing base layer.
Joint Reinforcement:
Apply crack-resistant tape and a flexible leveling compound to the joints between boards when using hard finishes like ceramic tiles. This improves ther esistance to cracking and, thus, tiles do not get cracked along the board joints.